The Commercial Court of the Chernivtsi Region collected UAH 16.97 million in fines from the LLC "Taktyk Pro" in favor of the state-owned enterprise "Defense Procurement Agency". The reason was the delay in the delivery of summer field suits and fire-resistant overalls. The court made its decision on November 4 and 9.
Two contracts and two deadlines
At the end of 2024, the State Rear Operator, whose legal successor is the Defense Procurement Agency, ordered 45,000 summer field suits from the company at UAH 1,499.9 per piece. The cost of the contract amounted to UAH 67.49 million.
In January 2025, a second contract was signed for fire-resistant overalls for the crews of combat vehicles for UAH 7,172 per unit for the amount of UAH 71.72 million.
According to both contracts, the supplier violated the deadlines. Suits were delivered up to 161 calendar days late, overalls - more than 100 days late.
The court did not recognize force majeure as an excuse
The company explained the delay as force majeure: after a downpour on July 28, 2025, the equipment temporarily stopped. According to the certificate of the Chamber of Commerce, these circumstances lasted until August 12.
The court noted that the delay began even before this event. Among the reasons, he cited lagging behind the production schedule and the conclusion of several large government contracts without proper calculation of production reserves.
According to the first contract, UAH 6.55 million in penalties and fines were collected from the company, according to the second - UAH 10.42 million. "Taktik pro" is registered in Chernivtsi, its founder is the "Economics" venture fund.
We will remind: the Commercial Court of Kyiv ordered "Ukrtak.YU" LLC to pay UAH 35 million in fines to the Defense Procurement Agency for late delivery of body armor.